Jurong Shipyard restores jack-up rig to upright position
They will now focus on investigations into the cause of the tilting.
Sembcorp Marine announced that Jurong Shipyard has successfully restored and floated the jack-up rig that tilted on 3 December 2012 to its original upright position following planned recovery and restoration operations on 14 January 2013.
Meanwhile repairs and restoration work will commence upon lifting of the stop-work order.